Gallery

Take part of our "fun" time!

Fema Cleaning
Septic work
Excavation and soil work
Footings
Foundations Footing
1st Foundations
Foundations
First Panel
StandingPanels Panel
Pre window
Concrete Day
Pouring Concrete
Pouring Concrete
Fire Sprinkler System on the roof 1
Fire Sprinkler System on the roof 3
Torching Panels
Reinforcement2
Reinforcement
Support
Installation of the windows
Gutter
Solar Panels Channels
Pouring concrete on walls
Electrical Junction box
Closing inspection validated
Last pouring on the wall
Conduits before concrete floor
Electricity and light concrete on the floor
Radiant Heating pipes on the floor
Exterior paint
Concrete Mess!
Installation solar system
Work on Hat Channel and ceiling electricity
Ceiling Sheetrock
Tiles
Moving in!